Section 25 - Area 10

Content

Construction Start: May 18, 2020

Construction Completion: November 2020

$6.5M investment funded by the City’s Water & Sewer Bond

  • Concrete road reconstruction with new approaches for each home
  • Water main replacement
  • Combined sewers will be separated, and sanitary flow will be directed to the new pump station at 10 Mile & Pierce
  • Storm leads will be made available for each home to connect sump pump lines
  • Sidewalk ramps will be upgraded to meet the American Disabilities Act guidelines
  • Project will be constructed in stages to reduce the impact on residents