All City of Southfield offices and facilities (excluding the 46th District Court) will remain closed to the public until at least Monday, March 15, 2021 or further notice in accordance with the most recent state of Michigan public health order. All essential public safety and public works services and departments continue to function as normal. Residents can still conduct most city business online and through City Hall’s main drop box 24/7 as well as via phone during the City Hall regular business hours, Monday-Friday from 8 a.m.- 5 p.m.
Section 25 - Area 10
Content
Construction Start: May 18, 2020
Construction Completion: November 2020
Restoration and Punchlist Completion: Spring 2021
$6.5M investment funded by the City’s Water & Sewer Bond
- Concrete road reconstruction with new approaches for each home
- Water main replacement
- Combined sewers will be separated, and sanitary flow will be directed to the new pump station at 10 Mile & Pierce
- Storm leads will be made available for each home to connect sump pump lines
- Sidewalk ramps will be upgraded to meet the American Disabilities Act guidelines
- Project will be constructed in stages to reduce the impact on residents