Section 15 – Evergreen Trail

Section 15 - Evergreen Trail Subdivision

Construction Start: June 18, 2018
Construction Completion: November 2018
  • Water main replacement throughout
  • Winchester – concrete road removed, replaced in asphalt with traffic calming measures (see presentation for details)
  • Roundabout at Winchester and Devonshire
  • Berkshire (Ledgestone to Winchester) – reconstruction in asphalt
  • Ledgestone, Larkmoor, Brookshire, Harbor – spot concrete repairs with some longer segments of reconstruction
  • $4.8M investment paid for with Water funds and Southfield Street Improvements Bond funds 

Construction Details
  • One-way traffic access on Winchester during construction
  • Winchester work occurs first followed by Evergreen Trail subdivision work
  • Week of June 18th and week of June 25th
    • Preconstruction video
    • Tree removals
    • Sawcutting existing concrete pavement 
  • Week of July 9th
    • Set up traffic controls
    • Start Winchester pavement removals
    • Start water main installation on Winchester

Evergreen Trail Subdivision Project Detail Presentation (PDF)
Roundabout FAQ (PDF)
Evergreen Trail Subdivision Construction Notice (PDF)
Traffic Plan During Construction (PDF)